Task Id Task Summary Start Date End Date Percent Complete Priority
831Validation of AFNI-PESTICA release cycle 12012-02-01 16:00* 2012-04-01 15:000%4
838Validation of AFNI-PESTICA release cycle 22012-06-02 00:00* 2012-08-02 00:000%3
909Validation of AFNI-PESTICA release cycle 32012-10-01 21:00* 2012-12-01 22:000%3