help > RE: Failed merging after parallel jobs - can't visualise results
May 13, 2021  12:05 AM | Alfonso Nieto-Castanon - Boston University
RE: Failed merging after parallel jobs - can't visualise results
Dear Mathilde,

Could you please try re-loading your project first, if merging has not finished correctly this will bring up a prompt asking you whether you want to merge the pending jobs and then you can simply proceed to merge them. If re-loading your project does not bring up this prompt, please let me know: a) if there is a 'pending jobs' notification visible in the main CONN gui; and b) if there in your conn project folder whether there are any files named conn_*.dmat (with the same root name as your conn project)

Thanks
Alfonso

Originally posted by Mathilde Argote:
Dear Conn experts,

I tried running 6 parallel jobs for preprocessing pipeline. It worked for 4 of them, and 2 failed. I clicked on the restart button for the 2 failed jobs and they successfully completed. Now, in the job history I can see that the 6 jobs are finished, but on the project the results don't appear. I can only visualise the results for the subjects treated by the 2 nodes which last finished. I think the problem might be caused by a failed merging attempt. I tried running "conn_process(9)" from the Matlab command window, and this message show up :

"Error using conn_process (line 2019)
Some conditions have not been processed yet. Re-run previous step"

I also tried renaming the info.mat file as I saw in a previous post it could fix the issue, but it didn't work either.

I would much appreciate some help !

For your knowledge, I'm using the CONN version 20b.

Thank you!

Threaded View

TitleAuthorDate
Mathilde Argote May 12, 2021
Herberto Dhanis May 27, 2021
Mathilde Argote May 21, 2021
RE: Failed merging after parallel jobs - can't visualise results
Alfonso Nieto-Castanon May 13, 2021
Mathilde Argote May 13, 2021